What You Pay For Before You Know If Your Toronto Addition Works

TLDR: Before you know whether your addition can be built for your budget, you should have spent a few hundred dollars, not tens of thousands. Check what your lot allows and what the build will cost first. Pay for a new survey (typically $2,800 to $3,200) only once you are committed. Then design, priced as it develops, with every payment to us credited forward into the $30,000 + HST deposit. The families who lose the most money are the ones who design first and ask what it costs last.

"We spent like $40,000 on design already"

That line came from a homeowner on a discovery call this fall, and the question behind it came up on more than half of the calls we reviewed. "The biggest cost would be the drawings. What's that running at?" "Is a request to the City enough for a survey? There's an old one online for a few hundred."

Underneath all of them is the same worry: how much do I have to spend before I find out whether this works?

Very little, if you spend it in the right order.

Why designing first and pricing last costs the most

The usual plan sounds sensible. Hire a designer, get the drawings done, then take them to three builders for quotes. It's different from a kitchen reno, where you get three quotes and pick the middle one.

Every so often a family comes to us with finished permit drawings and no idea what the build will cost. They trusted their designer to fit everything on the wish list and hoped it would land inside the budget. Some have spent tens of thousands of dollars on design. Others had a draftsperson produce poor drawings that still got a permit but did not have enough information to price. In the worst cases nobody told them what a project of that size should cost, and they could not build it, or had to go back for a new permit on a much smaller project. They assumed they'd design it, show builders, and get it quoted. That's not how it works.

The order is the problem. Nobody priced the plan while it was still cheap to change, and people get excited by design, arrive at something they are married to, and won't let it go. By the time the real number arrives, the money is spent and the drawings are finished.

We want people to fail quickly and iterate.

Six steps, from the zoning map to permit drawings, and what each costs

1. Check the zoning yourself first (free)

Start with the Toronto zoning map. The City's open data, plus whatever old survey of your property exists, gets you about 90% of the way to knowing what your lot allows: height, setbacks, how much floor area you have left.

Do not buy an old survey online at this stage. It will not be enough for an extension anyway, and it does not answer the question you actually have.

2. A feasibility check before anything is drawn (a few hundred dollars)

Before any design, someone who builds additions should tell you two things:

  • whether your plan fits the zoning or needs a Committee of Adjustment variance (which adds City fees and months to the timeline)

  • what it will cost to build, within about 5% to 10%

Our Feasibility Session does this in one hour. If the answer is no, or not for that budget, you have found out for a few hundred dollars.

3. A new survey, once you are committed ($2,800 to $3,200)

Any addition needs a current survey for the drawings and the permit. Expect $2,800 to $3,200, and expect to wait four to five weeks for it.

Book it only once you are going ahead. Until then, the zoning map and the old survey are enough for a first answer.

4. Design priced as it develops ($7,500 to $10,000 + HST)

This is where the plan becomes a design, with the budget checked at every step instead of at the end. For most projects that is our Design and Feasibility Sprint. It takes about four to six weeks when a new survey is needed, mostly waiting for the survey. The design itself takes two to three weeks after on-site measurements.

The fee is $7,500 to $10,000 + HST depending on the project, and it counts toward the $30,000 + HST deposit, like every payment you make to us before construction.

5. A Letter of Intent to start permit drawings ($7,500 + HST)

If the design and the budget work and you want to go ahead, the next step is a Letter of Intent, $7,500 + HST, which also counts toward the deposit. It is what starts the permit drawings. Together with the Sprint fee, it covers our work managing pre-construction: coordinating the survey, consultants, drawings and permit, and pricing every line with our trades.

6. Consultant fees for drawings, engineering and permit (tens of thousands of dollars)

Only now do the full permit drawings, structural design and mechanical design get done. These are the consultants' fees, paid as their work happens, separate from ours. For a typical addition, expect tens of thousands of dollars, depending on how detailed the drawings need to be and whether an interior designer is involved.

From the start of design to a permit usually takes 5 to 10 months. Where a project lands in that range depends on whether it needs a Committee of Adjustment variance, whether the Toronto and Region Conservation Authority (TRCA) is involved, how long the City takes to review the design and how many rounds of revisions it asks for. Every zoning or code comment round goes to the back of the queue, which is one more reason to settle the zoning in step 2.

The $30,000 + HST deposit comes last

Everything above happens before you sign a construction contract. The deposit is where you commit to the build, so it should come after you know the plan works and what it costs.

Our total deposit is $30,000 + HST, and every payment you have already made to us counts toward it: the Feasibility Session and report, the Sprint and the Letter of Intent. The balance is due when you sign the fixed-price contract. After that, payments follow the work: a mobilization draw for long-lead items like windows and steel, then draws at set milestones through the build.

The consultants, the survey, and City permit or Committee of Adjustment fees are separate, and you pay them as that work happens.

Buying a house to add on to? Get the range before the offer

If you are shopping for a house with an addition in mind, get a budget range before you make an offer. Once you buy, your hands are tied and you have carrying costs.

Why we don't bid on finished drawings

We work this way because the alternative costs our clients money. This decision isn't made on one call. There are multiple checkpoints, and we don't ask you to commit until you have the information.

That is also why we do not bid on finished drawings. If a set of drawings was never priced while it was being designed, the honest thing we can offer is a paid review of what it will really cost to build.

The quality of every BVM build is monitored by a Meagher, the family that started the company in 1997, and a Meagher runs pre-construction too.

What to ask any builder before you pay for design

Ask two questions. Will you price the design as it is drawn? And what will we have paid before we know whether this works? A builder who can only quote finished drawings is telling you the price comes last.

Key Takeaways

  • Check the zoning map first. It is free and answers most of "what does my lot allow."

  • Get a feasibility check, including a build cost usually within 5% to 10%, before paying for any design.

  • A new survey runs $2,800 to $3,200 and takes four to five weeks. Book it once you are committed, not before.

  • Price the design while it develops, not after the drawings are done.

  • If you are buying a house to add on to, get a budget range before you make the offer.

  • The deposit comes last: $30,000 + HST in total, and everything you paid us in pre-construction (Feasibility Session, Sprint, Letter of Intent) counts toward it.

Frequently Asked Questions

How much do drawings for a home addition cost in Toronto? For a typical addition, full design, engineering and permit drawings run tens of thousands of dollars, depending on the level of detail and whether an interior designer is involved. A survey adds $2,800 to $3,200. Spend on drawings only after the plan has been checked against zoning and priced.

Do I need a new survey before I start planning? Not to start. The City's zoning map and any old survey get you about 90% of the way to a first answer. You will need a current survey for the drawings and permit, so book one once you are committed to going ahead.

Can I get a builder to quote my finished drawings? You can, but a quote on drawings that were never priced during design often comes back far over budget, and by then the design money is spent. We price design as it develops instead, and offer a paid review for drawings that are already finished.

Book a Feasibility Session before you pay for drawings

In one hour, for a few hundred dollars, you will know what your lot allows, whether you need a variance, and what the build will usually cost within 5% to 10%. Book a Feasibility Session here.